Industrial Wastewater Treatment Success Stories
Successfully Treating Small Amounts of Winery Wastewater
Small Winery Case Study

The bottling facility needed to reduce their BOD from 6,000 ppm to 250 ppm or less. Having recently moved into the leased building,
It was soon realized that the POTW was not willing to let them discharge unless they could meet the 250 ppm BOD level.
Integrated Engineers, Inc. was retained to provide a packaged BioReactor to fit into their parking lot to reduce the 10,000 gpd wine water to meet the discharge limit.